| Task Name | Start | End | Duration (days) | ||
| Project Mobilization | 6/6/2022 | 6/13/2022 | 7 | ||
| Crew 1 & 2 Install Sanitary Sewer Dam Access Road | 6/14/2022 | 6/19/2022 | 5 | ||
| Crew 1 & 2 Install Sanitary Dam Access-EB Payne | 6/20/2022 | 6/22/2022 | 2 | ||
| Crew 1 & 2 Install Sanitary Sewer EB Payne-James St | 6/23/2022 | 6/30/2022 | 7 | ||
| Crew 1 & 2 Install Storm Sewer EB Payne | 7/5/2022 | 7/12/2022 | 7 | ||
| Crew 1 Install Sanitary Sewer James St | 7/13/2022 | 7/28/2022 | 15 | ||
| Crew 1 Install Sanitary Sewer Line C Sistrunk St | 7/29/2022 | 8/5/2022 | 7 | ||
| Crew 1 Install Sanitary Sewer Line D Alley | 8/6/2022 | 8/15/2022 | 9 | ||
| Crew 1 Install Sanitary Sewer Line E on James St | 8/16/2022 | 8/23/2022 | 7 | ||
| Crew 2 Install Gas Line Water Tank Area | 7/13/2022 | 8/3/2022 | 21 | ||
| Crew 1 Install Water Line W.Side of James St. Heading East | 8/24/2022 | 9/3/2022 | 10 | ||
| Crew 2 Install Gas Line W. Side of James St. Heading East | 8/4/2022 | 8/14/2022 | 10 | ||
| Crew 2 Install Gas Line Sistrunk St | 8/15/2022 | 8/22/2022 | 7 | ||
| Crew 2 Install Gas Line Alley | 8/23/2022 | 8/30/2022 | 7 | ||
| Crew 2 Install Gas Line on James St. | 8/31/2022 | 9/7/2022 | 7 | ||
| Crew 1 Install Water Line Sistrunk St. | 9/4/2022 | 9/11/2022 | 7 | ||
| Crew 2 Install Water Line Alley | 9/8/2022 | 9/15/2022 | 7 | ||
| Test, Cleanup and Demobilization | 9/15/2022 | 10/6/2022 | 21 |