Task Name |
Start |
End |
Duration (days) |
|
|
|
|
|
|
|
|
Project Mobilization |
6/6/2022 |
6/13/2022 |
7 |
|
|
Crew 1 & 2 Install Sanitary Sewer Dam Access Road |
6/14/2022 |
6/19/2022 |
5 |
|
|
Crew 1 & 2 Install Sanitary Dam Access-EB Payne |
6/20/2022 |
6/22/2022 |
2 |
|
|
Crew 1 & 2 Install Sanitary Sewer EB Payne-James St |
6/23/2022 |
6/30/2022 |
7 |
|
|
Crew 1 & 2 Install Storm Sewer EB Payne |
7/5/2022 |
7/12/2022 |
7 |
|
|
Crew 1 Install Sanitary Sewer James St |
7/13/2022 |
7/28/2022 |
15 |
|
|
Crew 1 Install Sanitary Sewer Line C Sistrunk St |
7/29/2022 |
8/5/2022 |
7 |
|
|
Crew 1 Install Sanitary Sewer Line D Alley |
8/6/2022 |
8/15/2022 |
9 |
|
|
Crew 1 Install Sanitary Sewer Line E on James St |
8/16/2022 |
8/23/2022 |
7 |
|
|
Crew 2 Install Gas Line Water Tank Area |
7/13/2022 |
8/3/2022 |
21 |
|
|
Crew 1 Install Water Line W.Side of James St. Heading East |
8/24/2022 |
9/3/2022 |
10 |
|
|
Crew 2 Install Gas Line W. Side of James St. Heading East |
8/4/2022 |
8/14/2022 |
10 |
|
|
Crew 2 Install Gas Line Sistrunk St |
8/15/2022 |
8/22/2022 |
7 |
|
|
Crew 2 Install Gas Line Alley |
8/23/2022 |
8/30/2022 |
7 |
|
|
Crew 2 Install Gas Line on James St. |
8/31/2022 |
9/7/2022 |
7 |
|
|
Crew 1 Install Water Line Sistrunk St. |
9/4/2022 |
9/11/2022 |
7 |
|
|
Crew 2 Install Water Line Alley |
9/8/2022 |
9/15/2022 |
7 |
|
|
Test, Cleanup and Demobilization |
9/15/2022 |
10/6/2022 |
21 |
|
|