Task Name Start End Duration (days)
Project Mobilization 6/6/2022 6/13/2022 7
Crew 1 & 2 Install Sanitary Sewer Dam Access Road 6/14/2022 6/19/2022 5
Crew 1 & 2 Install Sanitary Dam Access-EB Payne 6/20/2022 6/22/2022 2
Crew 1 & 2 Install Sanitary Sewer EB Payne-James St 6/23/2022 6/30/2022 7
Crew 1 & 2 Install Storm Sewer EB Payne 7/5/2022 7/12/2022 7
Crew 1 Install Sanitary Sewer James St 7/13/2022 7/28/2022 15
Crew 1 Install Sanitary Sewer Line C Sistrunk St 7/29/2022 8/5/2022 7
Crew 1 Install Sanitary Sewer Line D Alley 8/6/2022 8/15/2022 9
Crew 1 Install Sanitary Sewer Line E on James St 8/16/2022 8/23/2022 7
Crew 2 Install Gas Line Water Tank Area 7/13/2022 8/3/2022 21
Crew 1 Install Water Line W.Side of James St. Heading East 8/24/2022 9/3/2022 10
Crew 2 Install Gas Line W. Side of James St. Heading East 8/4/2022 8/14/2022 10
Crew 2 Install Gas Line Sistrunk St 8/15/2022 8/22/2022 7
Crew 2 Install Gas Line Alley 8/23/2022 8/30/2022 7
Crew 2 Install Gas Line on James St. 8/31/2022 9/7/2022 7
Crew 1 Install Water Line Sistrunk St. 9/4/2022 9/11/2022 7
Crew 2 Install Water Line Alley 9/8/2022 9/15/2022 7
Test, Cleanup and Demobilization 9/15/2022 10/6/2022 21