| Task Name | Start | End | Duration (days) | ||
| Project Mobilization | 100% | ||||
| Crew 1 & 2 Install Sanitary Sewer Dam Access Road | 100% | ||||
| Crew 1 & 2 Install Sanitary Dam Access Crossing EB Payne | 100% | ||||
| Crew 1 & 2 Install Sanitary Sewer EB Payne-James St | 100% | ||||
| Crew 1 & 2 Install Storm Sewer Crossing EB Payne | 100% | ||||
| Crew 1 Install Sanitary Sewer James St to Sistrunk | 100% | ||||
| Crew 1 Install Water Line E Side of James St heading W in Road | 100% | ||||
| Crew 1 Install Sanitary Sewer Line C in Sistrunk St | 8/1/2022 | 8/12/2022 | 11 | ||
| Crew 1 Install Water Line on Sistrunk St | 8/1/2022 | 8/12/2022 | 11 | ||
| Crew 1 Install Sanitary Sewer in James St Sistrunk to Ann in Road | 7/25/2022 | 7/30/2022 | 5 | ||
| Crew 1 Install Sanitary Sewer Line D in Alley | 8/13/2022 | 8/22/2022 | 9 | ||
| Crew 2 Install Sanitary Sewer Line E in James St in Road | 8/13/2022 | 8/20/2022 | 7 | ||
| Crew 2 Install Gas Line Water Tank Area | 100% | ||||
| Crew 2 Install Gas Line W. Side of James St.heading East in Road | 100% | ||||
| Crew 2 Install Water Line James St.from Sistrunk to S. Ann in Road | 7/25/2022 | 7/30/2022 | 5 | ||
| Crew 2 Install Gas Line in Alley | 8/31/2022 | 9/7/2022 | 7 | ||
| Crew 2 Install Gas Line in James St | 9/7/2022 | 9/14/2022 | 7 | ||
| Crew 2 Install Water Line in Alley | 8/23/2022 | 8/30/2022 | 7 | ||
| Test, Cleanup and Demobilization | 9/15/2022 | 10/6/2022 | 21 |