Task Name |
Start |
End |
Duration (days) |
|
|
Project Mobilization |
|
|
100% |
|
|
Crew 1 & 2 Install Sanitary Sewer Dam Access Road |
|
|
100% |
|
|
Crew 1 & 2 Install Sanitary Dam Access Crossing EB Payne |
|
|
100% |
|
|
Crew 1 & 2 Install Sanitary Sewer EB Payne-James St |
|
|
100% |
|
|
Crew 1 & 2 Install Storm Sewer Crossing EB Payne |
|
|
100% |
|
|
Crew 1 Install Sanitary Sewer James St to Sistrunk |
|
|
100% |
|
|
Crew 1 Install Water Line E Side of James St heading W in Road |
|
|
100% |
|
|
Crew 1 Install Sanitary Sewer Line C in Sistrunk St |
8/1/2022 |
8/12/2022 |
11 |
|
|
Crew 1 Install Water Line on Sistrunk St |
8/1/2022 |
8/12/2022 |
11 |
|
|
Crew 1 Install Sanitary Sewer in James St Sistrunk to Ann in Road |
7/25/2022 |
7/30/2022 |
5 |
|
|
Crew 1 Install Sanitary Sewer Line D in Alley |
8/13/2022 |
8/22/2022 |
9 |
|
|
Crew 2 Install Sanitary Sewer Line E in James St in Road |
8/13/2022 |
8/20/2022 |
7 |
|
|
Crew 2 Install Gas Line Water Tank Area |
|
|
100% |
|
|
Crew 2 Install Gas Line W. Side of James St.heading East in Road |
|
|
100% |
|
|
Crew 2 Install Water Line James St.from Sistrunk to S. Ann in Road |
7/25/2022 |
7/30/2022 |
5 |
|
|
Crew 2 Install Gas Line in Alley |
8/31/2022 |
9/7/2022 |
7 |
|
|
Crew 2 Install Gas Line in James St |
9/7/2022 |
9/14/2022 |
7 |
|
|
Crew 2 Install Water Line in Alley |
8/23/2022 |
8/30/2022 |
7 |
|
|
Test, Cleanup and Demobilization |
9/15/2022 |
10/6/2022 |
21 |
|
|