Task Name Start End Duration (days)
Project Mobilization 100%
Crew 1 & 2 Install Sanitary Sewer Dam Access Road 100%
Crew 1 & 2 Install Sanitary Dam Access Crossing EB Payne 100%
Crew 1 & 2 Install Sanitary Sewer EB Payne-James St 100%
Crew 1 & 2 Install Storm Sewer Crossing EB Payne 100%
Crew 1 Install Sanitary Sewer James St to Sistrunk 100%
Crew 1 Install Water Line E Side of James St heading W in Road 100%
Crew 1 Install Sanitary Sewer Line C in Sistrunk St 8/1/2022 8/12/2022 11
Crew 1 Install Water Line on Sistrunk St 8/1/2022 8/12/2022 11
Crew 1 Install Sanitary Sewer in James St Sistrunk to Ann in Road 7/25/2022 7/30/2022 5
Crew 1 Install Sanitary Sewer Line D in Alley 8/13/2022 8/22/2022 9
Crew 2 Install Sanitary Sewer Line E in James St in Road 8/13/2022 8/20/2022 7
Crew 2 Install Gas Line Water Tank Area 100%
Crew 2 Install Gas Line W. Side of James St.heading East in Road 100%
Crew 2 Install Water Line James St.from Sistrunk to S. Ann in Road 7/25/2022 7/30/2022 5
Crew 2 Install Gas Line in Alley 8/31/2022 9/7/2022 7
Crew 2 Install Gas Line in James St 9/7/2022 9/14/2022 7
Crew 2 Install Water Line in Alley 8/23/2022 8/30/2022 7
Test, Cleanup and Demobilization 9/15/2022 10/6/2022 21