1 Mobilization 5/19/23 2 Day(s) Day(s)
1

Little Rd/McArthur
Connection & Fire Hydrant
5/22/23 1 Day(s) Day(s)
1

Cut Road/Install 3″ & 6″ T &
Valve
5/23/23 1 Day(s) Day(s)
600
6″ PVC 5/24/23 1 Day(s) Day(s)
1

Opencut Herren St to
Patterson
5/25/23 1 Day(s) Day(s)
Seed & Hay
5/26/23 1 Day(s) Day(s)
Memorial Day
5/29/23 1 Day(s) Day(s)
600
Opencut Patterson,6″ PVC 5/30/23 1 Day(s) Day(s)
1,000
6″ PVC to Katie Lane 5/31/23 1 Day(s) Day(s)
300

Opencut Little Road at Katie
Lane, 6″ PVC Pipe
6/1/23 1 Day(s) Day(s)
Seed & Hay
6/2/23 1 Day(s) Day(s)
930
Katie Lane 4″ PVC 6/5/23 1 Day(s) Day(s)
Pressure Test/BacT
6/6/23 2 Day(s) Day(s)
Seed & Hay
6/9/23 1 Day(s) Day(s)
Services- Reconnection
&Connections
6/12/23 9 Day(s) Day(s)
Seed & Hay
6/23/23 1 Day(s) Day(s)
Tie-ins/Pavement Patch
6/26/23 5 Day(s) Day