1 Mobilization 5/19/23 2 Day(s) Day(s)
1
Little Rd/McArthur
Connection & Fire Hydrant 5/22/23 1 Day(s) Day(s)
1
Cut Road/Install 3″ & 6″ T &
Valve 5/23/23 1 Day(s) Day(s)
600 6″ PVC 5/24/23 1 Day(s) Day(s)
1
Opencut Herren St to
Patterson 5/25/23 1 Day(s) Day(s)
Seed & Hay 5/26/23 1 Day(s) Day(s)
Memorial Day 5/29/23 1 Day(s) Day(s)
600 Opencut Patterson,6″ PVC 5/30/23 1 Day(s) Day(s)
1,000 6″ PVC to Katie Lane 5/31/23 1 Day(s) Day(s)
300
Opencut Little Road at Katie
Lane, 6″ PVC Pipe 6/1/23 1 Day(s) Day(s)
Seed & Hay 6/2/23 1 Day(s) Day(s)
930 Katie Lane 4″ PVC 6/5/23 1 Day(s) Day(s)
Pressure Test/BacT 6/6/23 2 Day(s) Day(s)
Seed & Hay 6/9/23 1 Day(s) Day(s)
Services- Reconnection
&Connections 6/12/23 9 Day(s) Day(s)
Seed & Hay 6/23/23 1 Day(s) Day(s)
Tie-ins/Pavement Patch 6/26/23 5 Day(s) Day